Training course description:
Objectives |
The objectives of the sewer inspection, rehabilitation and management course are to impart the participants knowledge about the management of waste water network systems. The participants will be trained to inspect, to evaluate and to renovate sewage networks with the most efficient and sustainable methodology. |
Content | Sewer inspection, Evaluation of sewer conditions, Basic of structural sewer conditions, Planning of rehabilitation projects, Rehabilitation methods: CIPP and Large sewers |
Target Group and selection criteria |
Project Managers and engineers of sewage companies |
N° of participants | Max 12 participants |
Trainer | 1.Mr. Saša Kosanović, Agra d.o.o., 2.Mr. Sasa Petričić. kaProjekt d.o.o. |
Training Methods | Theoretical lessons, power point presentations, on site workshop, group activities, practical exercises |
Language/Material | Croatian lessons |
Evaluation | By feed-back discussion and in written form |
Partner Organisations | GWP Rainer Kiel Kanalsanierung GmbH, SAERTEX multiCom GmbH, Agra d.o.o. (IBAK representative) |
Training course schedule: Day 1
DAY 1 | ||
10:00–11:00 | Welcome Introduction of participants Outline of the course Expectations of the participants |
Group talk Hand-out of training material Flip chart to collect expectations |
11:00–11:30 | BREAK | |
11:30–13:00 | Sewer inspection (theoretical in accordance with EN13508-2 - Types and characteristics of sewer damages (e.g. cracks, broken fragments, offset joints, corrosion, leaking laterals, settlements, etc) |
Presentations |
13:00–14:00 | LUNCH | |
14:00–15:30 | Sewer inspection (theoretical in accordance with EN13508-2 - Optical inspection - Recording key and code system for different type of damages |
Presentations |
15:30–16:00 | BREAK | |
16:00–16:30 | Sewer inspection - Exercise of capturing actual sewer conditions on the basis of a CCTV record |
Group Work |
16:30–17:00 | Sewer inspection -Exercise of capturing actual sewer conditions on the basis of a CCTV record |
Group Presentation |
5 hours |
Training course schedule: Day 2
DAY 2 | ||
09:00–10:30 | Sewer inspection (practical) -CCTV of test track (sewer) provided by ViK Karlovac |
Group exercise |
10:30–11:00 | BREAK | |
11:00–13:00 | Sewer inspection (practical) -CCTV of test track (sewer) provided by ViK Karlovac |
Group exercise |
13:00–14:00 | LUNCH | |
14:00–14:45 | Rehabilitation Methodologies -Overview of rehabilitation technologies -Differences between Repair, Renovation and Re-new technologies -Advantages, Disadvantages and area of application of different technologies |
Group work Mind mapping Flip chart Presentations |
14:45-15:30 | Planning of rehabilitation projects Part 1 -Information requirements to plan a sewer rehabilitation project -Assessment of actual site information as: public place, traffic, customers, local businesses and environment -Accessibility of construction site |
Group exercise Presentations |
15:30-16:00 | BREAK | |
16:00-17:30 | Site visit If possible and in regards to H&S and ViK policy the group will enter a sewer. |
Group |
6,5 hours |
Training course schedule: Day 3
DAY 3 | ||
09:00–09:45 | Summary of Day 1 and Day 2 | Summary by group exercise Questionnaire |
09:45–10:30 | Planning of rehabilitation projects Part 2 -Choice of rehabilitation technology -Technical considerations to apply rehabilitation technology -Effects of ground conditions and groundwater levels -Advantages of trenchless technologies |
Group exercise Presentations |
10:30–11:00 | BREAK | |
11:00–11:45 | Basics of structural sewer condition -Actual pipe condition as per ATV A-127; -Particular characteristics of condition I, II and III -Parameter of structural liner calculations (groundwater level, loadings, condition assessment I, II or III, E-Module, Liner thickness, etc |
Group exercise Presentations |
11:45–12:30 | Rehabilitation technology CIPP -Overview -Requirements (labour, equipment, vehicle, planning information) -Type of installation material -Area of application -Installation procedure -Internal / external factors |
VIDEO presentation Power Point presentation |
12:30–13:30 | LUNCH | |
13:30-14:30 | Rehabilitation technology large sewers -Rehabilitation of large sewers > ND 800mm -Requirements (labour, equipment, vehicle, planning information) -Type of installation material -Area of application -Installation procedure -Internal / external factors |
Presentations |
14:30–15:00 | Summary of course content | Active questioning Presentations |
15:00-16:00 | EXAM | |
5,5 hours | Complete training: 17 hours |